|
Special Considerations and Tips to Achieve
Professional Wood Floor Installation Results
"In-use Moisture Content"
Differences of more than 4% between the expected in-use average
moisture content of flooring and the in-use average moisture content
of under-floor construction are likely to cause problems such as
cupping. The greater the difference the more severe the problems.
A significant difference of 8% or more may result in buckling of
the floor when the under-floor is the higher moisture content.
Storage and handling practices
Precautions concerning moisture conditions must be observed.
In particular, the building should be closed in with all doors and
windows in place and all concrete, masonry and plaster thoroughly
dry. On exterior walls install a vapor retarder within the wall
system. Check with an HVAC engineer for proper placement.
Finishing should proceed within 1-3 weeks
after installation is completed.
Longer periods of exposure to job site conditions can result
in future problems and include increased risk of damage from contaminants.
Stager Plank Lengths.
For best appearance always use long flooring planks at entrances
and doorways. Incorporate as many shorter pieces as possible at
random throughout the floor, in closets, areas under cabinets and
planned area rugs. Randomly stagger the planks. Avoid breaking the
blank ends in a line or a definable pattern.
Put a "frame" around obstructions.
You can give a much more professional and finished look to a
plank flooring installation if you "frame" hearths and other obstructions,
using mitered joints at the corners.
Use only sound, straight boards for sub-floors.
The quality of the sub-flooring will affect the finished flooring.
Use only square edge 3/4" dressed boards no wider than 6". Boards
which have been used for concrete form work are often warped and
damp and should not be used.
Don't pour concrete after flooring is installed.
Concrete basement floors are sometimes poured after hardwood
flooring has been installed. However, many gallons of water from
drying concrete are evaporated into the house atmosphere where it
may be absorbed by hardwood flooring and other wood components.
This is not a recommended building practice since excessive moisture
will cause problems with wood floors and other woodwork. Wood flooring
should not be installed until after all concrete and plaster work
are completed and dry.
Put voids between screeds to good use.
Masonry insulation fill, normally used in hollow concrete blocks,
can be poured between the screeds of a slab installation to give
additional moisture protection and deaden the drumming sound that
sometimes occurs from foot traffic.
Sound deadening in multi-story building.
Noise transmission from an upper to a lower floor can be reduced.
Nail sub-floor to the joists in the normal manner and cover this
with 1/2" or thicker cork or insulation board laid in mastic. Cover
this with another 3/4" plywood sub-floor also laid in mastic. Nail
the finish plank floor to the plywood. Note that specifications
for some high-rise apartment buildings call for other types of sound-deadening
construction.
Mastics and trowels.
Different Manufacturers Products. Do not randomly mix different
manufacturers' products. Use transition areas such as doorways to
separate the different manufacturers.
T&G Planks on Flooring, Walls and
Ceilings.
The planks can be nailed direct to the studs for a horizontal
application. For vertical or diagonal application to a stud
wall, nail 1 1/2" thick furring strips (2 x 4s) to the studs at
12" spacing and nail the flooring to these strips.
For masonry walls, fasten lengths of 2 x 4s on 12" centers to
the walls with concrete fasteners designed for the expected
load. Nail size and schedule are the same as for flooring
applications. Click here for detailed paneling application guide
(pdf).
[ Back ] [ Next ]
|